Current Projects

The project information listed below was updated on April 17th, 2023. Schedules are subject to change as conditions warrant. Click on a project name below for more information. If you have specific questions, please email DPW at dpwinfo@northamptonma.gov. For weekly construction updates and other announcements, please visit DPW's News Flash.

Back to top

Bridge Street School Safe Routes to School

Back to top

Damon Road Reconstruction

Back to top

Dryads Green Extension Drainage & Slope Improvements

  • Drainage and slope improvements from the end of Dryads Green to the Mill River
  • Design, permitting and contract documents prepared by GZA GeoEnvironmental, Inc.
  • Permit approval completed in Winter 2023
  • Project bidding and award anticipated in Spring 2023 with construction in Summer/Fall 2023

Back to top

Federal Emergency Management Agency (FEMA) Levee Certification

  • Engineering evaluation to establish capital improvement priorities
  • Accreditation that the flood control system meets FEMA requirements for flood protection for updated Flood Insurance Rate Maps (FIRM) under development by FEMA
  • Project awarded to GZA GeoEnvironmental, Inc.
  • Multi-year project
  • Phase 1 complete and supported by $315,000 state Municipal Vulnerability Preparedness (MVP) grant
  • Engineering evaluations were submitted to FEMA in March 2023 and are under review

Back to top

Flood Control Vegetation Management

  • Miscellaneous mechanical vegetation management on the flood control structures to maintain the levees in conformance with US Army Corps of Engineers requirements
  • Contract documents prepared by DPW Engineering, funded by City’s Stormwater & Flood Control Enterprise
  • Project awarded to Cain’s Mechanical LLC
  • Three-year contract
  • Periodic work is ongoing late spring through late fall, 2022-2024

Back to top

Gothic Street & Texas Road Drainage Improvements

  • Drainage improvements on Gothic Street at the James House Parking Lot and along Texas Road
  • Design by DPW Engineering, funded by City’s Stormwater & Flood Control Enterprise
  • Contract awarded to Baltazar Contractors, Inc.
  • Construction substantially complete with final completion anticipated in Spring 2023

Back to top

Hockanum Road Flood Control Pump Station

  • Phase 1 facility improvements
  • Work includes electrical system upgrades, removal of existing underground fuel storage tanks and replacement with above ground storage tanks and miscellaneous building improvements
  • Designed by Tighe & Bond
  • Contract awarded to Bay State Regional Contractors, Inc.
  • Construction completion is anticipated in Summer 2023

Back to top

Interstate 91 - Bridges Over US Route 5, B&M Railroad and Hockanum Road

  • Bridge and roadway improvements at Exit 23 (formerly Exit 18)
  • MassDOT project #606552
  • Work includes bridge replacement as noted and roadway & sidewalk improvements at Exit 23 where it meets US Route 5 (Mount Tom Road)
  • Project awarded to J.F. White Contracting Co.
  • Construction began in Summer 2021 and will take several years to complete
  • Questions about the project should be directed to MassDOT District 2

Back to top

Landfill Flare

  • Replacement of existing enclosed flare with a candlestick flare as gas generation continues to decline at the landfill on Glendale Road which closed in 2013
  • Designed by Weston & Sampson
  • Project awarded to Product Recovery Management, Inc
  • Construction is anticipated to be complete in Fall 2023

Back to top

Locust Street & SVAHS Drainage Improvements

  • Construction of an outfall and stilling basin to relieve capacity constraints in the Locust Street drainage system, including replacement of a failed drain manhole in Locust Street
  • Design and permitting by Northampton DPW
  • The project is out to bid with bids due April 26, 2023
  • Construction anticipated in Summer 2023

Back to top

Main Street (downtown) Redesign

  • Redesign of Main Street from Market/Hawley Streets to West Street
  • MassDOT project #609286
  • Proposed safety and infrastructure improvements including: travel lane realignment, parking reconfiguration, dedicated bike lanes, expanded sidewalks, new traffic signals, stormwater improvements, landscaping, amenities and water and sewer main replacement
  • Primary design by Toole Design; water and sewer design by Tata & Howard
  • 25% design was submitted to MassDOT for review in January 2022
  • 25% Design Public Hearing scheduled for Wednesday, April 26, 2023, 6:00 - 8:00 p.m. 25% Design Plan (pdf)Public Hearing Flyer (pdf)
  • See the Picture Main Street StoryMap for latest news and project background & history
  • Currently scheduled for bidding on the 2025 Transportation Improvement Program (TIP), supported by federal and state funding
  • Water and sewer design and replacement funded by City's Sewer and Water Enterprises
  • Questions about the project should be directed to the Planning & Sustainability Department

Back to top

Main Street (Florence) Streetscape Improvements

  • Streetscape improvements at various locations including ADA compliant curb ramps, sidewalk replacement, tree pits, street furniture, curbing and drainage
  • Designed by Berkshire Design Group
  • Contract awarded to Gomes Construction Company, Inc
  • Construction anticipated to be complete in Spring 2023
  • Questions about the project should be directed to the Planning & Sustainability Department

Back to top

Manhan Rail Trail Retaining Wall

  • Construction of a gabion retaining wall to buttress and reinforce a deteriorating stone retaining wall across from Veterans Field off West Street
  • Designed by Berkshire Design Group
  • Project awarded to Clayton D. Davenport Trucking
  • Construction is underway and is anticipated to be complete in Spring 2023; a bike path detour (pdf) will be required during construction
  • Questions about the project should be directed to the Planning & Sustainability Department

Back to top

North Elm Street - Northampton High School Traffic Study

  • Traffic study to review pedestrian and bicycle safety, vehicular traffic flow, parking conditions, and traffic controls in the vicinity of Northampton High School
  • Data collection and analysis by Fuss & O’Neill
  • Results of NHS Traffic Study, December 2022 (pdf)

Back to top

Ryan and West Whately Reservoirs

  • Dam rehabilitation & spillway improvements
  • Design & permitting ongoing by GZA GeoEnvironmental, Inc.
  • Design & permitting supported by $250,000 Mass EEA grant
  • Construction start anticipated in Fall 2023

Back to top

Wastewater Treatment Plant - Phase 2

  • Major upgrades to sludge processing equipment and building, plant water system, electrical feeds and implementation of a SCADA system
  • Design by Woodard & Curran
  • Bidding in Spring 2023
  • Construction anticipated to begin in Fall 2023 and be completed in Spring 2025
  • Supported by Clean Water State Revolving Fund (CWSRF)

Back to top

Water System - Leeds High Pressure Area Alterations

  • Water System Improvements along Haydenville Road and River Road
  • Work includes a new pressure reducing valve (PRV) and building for the transmission main and new interconnections to Leonard and East Center Streets
  • Design by Tata & Howard, funded by the City’s Water Enterprise
  • Contract awarded to GEG Construction, Inc.
  • Construction anticipated to be complete in Spring 2023

Back to top

Winter Street Reconstruction

  • Full depth roadway reconstruction, including water and sewer utilities and sidewalks
  • Design and permitting by DPW Engineering, funded by City paving bond and City’s Water and Sewer Enterprises
  • Project awarded to Caracas Construction Corp.
  • Construction is underway and is anticipated to be complete in Summer 2023

Back to top