Posted on: June 2, 2023

[ARCHIVED] Construction for the Week of June 5th

Highway Division Updates

  • Last week, the Highway Division:
    • Repaired potholes on Riverside Drive and Strong Avenue
    • Graded gravel roads at Maines Field
    • Installed, repaired and/or replaced signs on Bancroft Road, Crescent Street, Franklin Street, Hillside Road, Industrial Drive and New South Street
    • Installed pedestrian paddles on Main Street and at the Locust Street Transfer Station
    • Patched trench cuts on Bridge Street and Market Street
    • Swept streets in downtown, as well as in Florence Center
    • Completed Summer on Strong installation and added planters to Main Street
  • Annual ward street sweeping operations have begun in Ward 5
    • Wards will be swept in the following order this year: 5, 4, 3, 2, 1, 7, 6
  • To report a pothole, please submit a request via the Pothole Repair Form; the largest potholes are filled first to alleviate hazards to vehicles; as hazards arise and are identified, they will be addressed

Bridge Street School Safe Routes to School

  • MassDOT has contracted with Gomes Construction Company, Inc. to complete improvements that will enhance pedestrian safety near Bridge Street School
  • The project will upgrade sidewalks, curbing and accessible ramps on Parsons Street and portions of Hawley Street; upgrade the pedestrian crossing on Bridge Street near Parsons Street including RRFBs; and reconstruct the intersection of Pomeroy Terrace with Bridge Street to install a raised crosswalk and to improve drainage
  • The project is scheduled to be complete in Summer 2023
  • The Contractor has demobilized and will remobilize in late June, after school is out, to complete the project
  • On-street parking prohibitions have been removed until the Contractor returns in late June to complete the project
  • Questions about the project should be directed to MassDOT District 2, project #609915

Damon Road Reconstruction

  • MassDOT has contracted with Gagliarducci Construction, Inc. to reconstruct Damon Road from the bike path to just beyond the intersection with King Street, North King Street and Bridge Road
  • The project will provide intersection and traffic signal improvements, extended sidewalks, a shared use path and other safety improvements
  • The project is scheduled to be completed by the end of 2023
  • The Contractor will be installing new water main at the intersection of King Street and Damon Road and granite curbing on the easterly end of Damon Road this week
  • Motorists should expect delays with traffic shifts at the intersection and alternating one-way traffic for curb installation
  • Questions about the project should be directed to MassDOT District 2, project #608236

Dryads Green Extension Drainage & Slope Improvements

  • The City has contracted with Geeleher Enterprises Inc. to construct drainage and slope improvements from the end of Dryads Green Extension to the Mill River; work also includes roadway drainage improvements in the vicinity of 49, 50, 55, 57 & 59 Dryads Green
  • Construction is anticipated to begin in late June and continue through the summer
  • The path from Dryads Green Extension to the Mill River remains closed until further notice; construction will also temporarily close the walking path along the Mill River

I-91 Bridges over Route 5, the Railroad and Hockanum Road

  • MassDOT has contracted with J.F. White, Inc. to construct roadway improvements to I-91 and at Exit 23 (formerly Exit 18)
  • The project will replace the I-91 bridges over Route 5, the Railroad and Hockanum Road and construct safety and signal improvements at the exit interchange
  • The project is scheduled to be completed in phases by 2025
  • I-91 southbound, no traffic impacts are anticipated this week
  • I-91 northbound, right lane closure Tuesday through Thursday from 9:00 a.m. to 2:00 p.m
  • Route 5, lane shifts as needed Tuesday from 7:00 a.m. to 3:00 p.m. for traffic signal work; police details will assist with traffic control
  • Hockanum Road, no traffic impacts are anticipated this week
  • Questions about the project should be directed to MassDOT District 2, project #606552

Leeds Pressure Reducing Valve

  • The City has contracted with GEG Construction for water system improvements that include an above grade pressure reducing valve (PRV) connected to the 36-inch transmission main in Haydenville Road across from Scotti’s
  • The project will allow for the eventual demolition of the Audubon Road water storage tank
  • The project is scheduled to be completed in Spring 2023
  • Final site work may continue this week

Levee Toe Drain Improvements

  • The City has contracted with Ludlow Construction Co., Inc. for the installation of manholes along the land side of both the Connecticut and Mill River levee systems
  • The project involves the installation of 28 new manholes and inspection of the toe drains running parallel to the levees via CCTV
  • Manhole installations and pipe inspections via CCTV are complete
  • A pipe repair adjacent to Venturers Field Road and final loam & seed restoration will occur in Spring 2023

Levee Vegetation Management

  • The City has contracted with Cain’s Mechanical LLC for vegetation management at various locations throughout the levee and flood control system on both the Connecticut and Mill Rivers
  • Work to mechanically remove unwanted woody growth and fallen trees and localized placement of rip rap for slope stabilization will be undertaken periodically system wide throughout the growing season
  • The Contractor will continue removing woody vegetation along riprap slopes of the Mill River Diversion Channel this week

Locust Street & SVAHS Drainage Improvements

  • The City has contracted with Clayton D. Davenport Trucking, Inc. to construct an outfall and discharge basin to relieve capacity constraints in the Locust Street drainage system; work includes the replacement of a failed drain manhole in Locust Street
  • Construction is anticipated to begin in late June and continue through the summer

Main Street, Florence Streetscape Improvements

  • The City has contracted with Gomes Construction Co., Inc. for streetscape improvements along Main Street in Florence from Maple Street to South Main Street
  • The project includes targeted sidewalk replacement, compliant accessible curb ramps, curb realignment at South Main Street, tree pits and street furniture
  • The project is complete
  • Questions about the project should be directed to the Planning & Sustainability Department

Manhan Rail Trail Retaining Wall

  • The City has contracted with Clayton D. Davenport Trucking, Inc. to construct a supplemental retaining wall on the Manhan Rail Trail near Veterans Field off West Street
  • The project includes constructing a gabion basket rock wall to buttress the existing stone retaining wall and filling an abandoned brick sewer with flowable fill to provide a sufficient foundation for the new wall
  • The project is complete
  • Questions about the project should be directed to the Planning & Sustainability Department

Winter Street Reconstruction

  • The City has contracted with Caracas Construction Corporation for the full depth reconstruction of Winter Street, including water & sewer mains and service connections and sidewalks
  • Construction is scheduled to be complete by Fall 2023
  • The Contractor will not be working on site this week
  • The schedule for final paving of the roadway and sidewalks is TBD

An overview of all current Public Works projects can be found by going to Current Projects.

Sign up for automatic notifications via the Notify Me system on the City's website. Please sign-in (at the top of the page) and then subscribe to the "Public Works" category under News Flash (at the bottom of the page).


Facebook Twitter Email

Other News in Public Works

Construction for the Week of October 2nd

Posted on: September 29, 2023