[ARCHIVED] Construction for the Week of February 12th

Highway Division Updates

  • Last week, the Highway Division:
    • Repaired potholes on Bardwell Street, Beacon Street, Lincoln Avenue, Market Street, Revell Ave, South Main Street and South Street
    • Removed, repaired and/or replaced signs on Bridge Road, Elm Street, Prospect Street and West Street
    • Repaired trench cuts on Stearns Court
  • Lovefield Street remains closed
  • Annual ward street sweeping operations will resume in the spring
  • To report a pothole, please submit a request via the Pothole Repair Form; the largest potholes are filled first to alleviate hazards to vehicles; as hazards arise and are identified, they will be addressed
  • To report an issue with a traffic sign, please submit a request via the Traffic Sign Issue Form

Dryads Green Extension Drainage & Slope Improvements

  • The City has contracted with Geeleher Enterprises Inc. to construct drainage and slope improvements from the end of Dryads Green Extension to the Mill River; work also includes roadway drainage improvements
  • The project is substantially complete
  • Snow storage should be avoided at the dead end so as not to compromise slope integrity
  • Public Works will be on-site continuing post-construction observations throughout the winter

I-91 Bridges over Route 5, the Railroad and Hockanum Road

  • MassDOT has contracted with J.F. White, Inc. to construct roadway improvements to I-91 and at Exit 23 (formerly Exit 18)
  • The project will replace the I-91 bridges over Route 5, the Railroad and Hockanum Road and construct safety and signal improvements at the exit interchange
  • The project is scheduled to be completed in phases by 2025
  • I-91 southbound:
    • Daytime right lane closure Monday through Friday this week, from 7:00 a.m. to 2:00 p.m., for site access
  • I-91 northbound:
    • No traffic impacts are anticipated this week
  • Route 5:
    • Lane shifts Monday through Friday this week, from 7:00 a.m. to 3:00 p.m., for deck work; two-way traffic will be maintained at all times
  • Hockanum Road:
    • No traffic impacts are anticipated this week
  • Questions about the project should be directed to MassDOT District 2, project #606552

Loudville Road

  • The City has contracted with Geeleher Enterprises Inc. to install a catch basin and drain pipe on Loudville Road in the vicinity of 81, 83 and 85 Loudville Road to address roadway drainage issues
  • Excavation work and drainage installations are complete
  • A partial road closure will be needed to install a temporary pavement patch sometime in the coming weeks
  • A permanent pavement patch will be installed in the spring

Winter Street Reconstruction

  • The City has contracted with Caracas Construction Corporation for the full depth reconstruction of Winter Street, including water & sewer mains and service connections and sidewalks
  • The project is substantially complete
  • Public Works and/or the Contractor will be on-site continuing post-construction inspections throughout the winter

Projects to Resume Spring 2024

An overview of all current Public Works projects can be found by going to Current Projects.

Sign up for automatic notifications via the Notify Me system on the City's website. Please sign-in (at the top of the page) and then subscribe to the "Public Works" category under News Flash (at the bottom of the page).


Facebook Twitter Email

Other News in Public Works

Annual Water Main Flushing

Posted on: March 30, 2026
City Seal Newsflash Image

Annual Water Quality Report

Posted on: March 11, 2026