Interactive Construction Updates Map - managed by the Mayor's Office
Highway Division Updates
- Last week, the Highway Division:
- Graded roads in Northampton Meadows
- Installed, removed, repaired and/or replaced signs on Cooke Avenue, Denniston Place, Elm Street, Finn Street, Florence Street, Hatfield Street, Henshaw Avenue, Mulberry Street, Paquette Avenue, Prospect Street and West Street
- Marked drain inlets for winter storm operations
- Sealed:
- Catch basins on Summerfield Street
- Driveway aprons on Allen Place, Cooke Avenue, Dimock Street, Dunphy Drive, Hockanum Road, Reservoir Road, Ryan Road and Woods Road
- Manholes on Bayberry Lane, Birch Lane, Diamond Court, Earle Street, Hillside Drive, Industrial Drive East, Ladyslipper Lane, Leeno Terrace, Locust Street, Matthew Drive, West Parsons Lane, West Street and Winterberry Lane
- Potholes on Gleason Road
- Trench cuts on Aldrich Street, Burts Pit Road, Federal Street, Front Street and Linden Street
- Water valves on Dimock Street, Gleason Road, Round Hill Road
- Trimmed brush along Westhampton Road (Route 66)
- Federal Street is reduced to one lane at the culvert crossing between Milton Street and Vernon Street until further notice
- Lovefield Street remains closed until further notice
- Annual ward street sweeping operations are complete and will resume in the spring; periodic/as-needed sweeping will continue through the fall
- To report a pothole, please submit a request via the Pothole Repair Form; the largest potholes are filled first to alleviate hazards to vehicles; as hazards arise and are identified, they will be addressed
- To report an issue with a traffic sign, please submit a request via the Traffic Sign Issue Form
Bancroft Road & Crescent Street Drain Repair
- The City has contracted with Geeleher Enterprises Inc. to repair a drain at the intersection of Bancroft Road and Crescent Street
- Work is expected to begin in the coming weeks
Dam & Flood Control System Vegetation Management
- The City has contracted with Cain’s Mechanical LLC for vegetation management on dams within the City’s watershed areas and at various locations throughout the levee and flood control system on both the Connecticut and Mill Rivers
- Work to mechanically remove unwanted woody growth and fallen trees and localized placement of rip rap for slope stabilization will be undertaken periodically system wide throughout the growing season
- The Contractor is scheduled to resume mowing operations in mid October
Damon Road Reconstruction
- MassDOT has contracted with Gagliarducci Construction, Inc. to reconstruct Damon Road from the bike path to just beyond the intersection with Bridge Road, King Street and North King Street
- The project will provide intersection and traffic signal improvements, extended sidewalks, a shared use path and other safety improvements
- Project completion is anticipated in Fall 2024
- The Contractor will be installing bounds, curb, driveways, loam, seed, signs and splitter islands at the Bridge Road-Damon Road-King Street-North King Street intersection; the right lane on King Street & North King Street may be closed and one way alternating traffic may be in place on Damon Road during construction hours (7:00 a.m. - 3:30 p.m.)
- Permanent pavement markings will be installed overnight in the coming weeks
- Questions about the project should be directed to MassDOT District 2, project #608236
Dryads Green Extension Drainage & Slope Improvements
- The City has contracted with Geeleher Enterprises Inc. to construct drainage and slope improvements from the end of Dryads Green Extension to the Mill River; work also includes roadway drainage improvements
- Construction is complete
- Public Works will be on-site continuing post-construction observations throughout the summer
- Minor site modifications will be installed in the coming weeks
Easthampton Road (Route 10) Water Main Replacement
- The City has contracted with Jack Goncalves & Sons, Inc to replace 650 feet of water main on Easthampton Road from Earle Street to Racing Mart/Shell
- Work is complete
Green Street - Smith College Geothermal Project
- Smith College is undertaking a campus-wide geothermal energy project
- The project includes the installation of underground distribution piping across several City streets
- Construction will continue on campus through November
I-91 Bridges over Route 5 (Mount Tom Road), Railroad and Hockanum Road
- MassDOT has contracted with J.F. White, Inc. to construct roadway improvements to I-91 and at Exit 23 (formerly Exit 18)
- The project will replace the I-91 bridges over Route 5, the Railroad and Hockanum Road and construct safety and signal improvements at the exit interchange
- Project completion is anticipated in Fall 2024
- I-91 southbound:
- Daytime left lane closure Monday through Thursday this week, from 6:00 a.m. to 2:00 p.m., for removal of temporary bridge
- Nighttime alternating lane and ramp closures Sunday through Thursday this week, from 7:00 p.m. to 5:00 a.m., for pavement markings installation; a detour will be in place during ramp closures
- I-91 northbound:
- Nighttime alternating lane and ramp closures Sunday through Thursday this week, from 7:00 p.m. to 5:00 a.m., for pavement markings installation; a detour will be in place during ramp closures
- Route 5:
- Daytime shoulder closure Monday through Friday this week, from 7:00 a.m. to 3:00 p.m., for pavement markings & sign installation
- Nighttime alternating lane and ramp closures Wednesday and Thursday this week, from 7:00 p.m. to 6:00 a.m., for pavement markings installation; a detour will be in place during ramp closures
- Hockanum Road:
- No traffic impacts are anticipated this week
- Questions about the project should be directed to MassDOT District 2, project #606552
King Street Corridor Traffic Signal Pole Painting
- MassDOT has contracted with a painting contractor, Polar Vortex, to paint the poles of the traffic signals at North & Summer Streets and Finn Street at both King and State Streets
- Work is scheduled to begin the week of October 21st and is anticipated to last approximately three (3) weeks
- Questions about the project should be directed to MassDOT District 2, project #607502
Pavement Resurfacing 2024
- The City has contracted with Northeast Paving for paving on the following streets: Bridge Road, Burts Pit Road, Chestnut Street, Dana Street, Look Park roundabout, Loudville Road, North Elm Street, North Loudville Road, North Main Street, North Maple Street and Spring Street
- The project also includes sidewalk reconstruction along several of the streets to be repaved and on North Main Street from Park Street to the Look Park roundabout, upgrades to curb ramps, new pavement markings, sign installation and speed hump & speed table installation (pdf) on Burts Pit Road, Meadow Street and Spring Street
- See Construction Notice (pdf) for more information
- Motorist should expect traffic delays; please seek alternate routes if possible
- The Contractor will continue with the following work this week:
- Paving surface/top course for roadways on Chestnut Street, Dana Street, North Elm Street and North Maple Street
- Installing flexible porous pavement by select trees on Chestnut Street, North Elm Street, North Main Street, North Maple Street and Spring Street
Rocky Hill Road (Route 66)
- The City has contracted with Geeleher Enterprises Inc. to repair a drain pipe near the Hampshire Jail & HOC
- Work also includes repairs to the east bound lane pavement, curbing and sidewalk
- The Contractor will dig test pits and install two (2) manholes this week; one way alternating traffic may be in place; a police detail will assist with traffic control
Rocky Hill Road, Ice Pond Outlet Improvements
- The City has contracted with Flynn Enterprises, Inc. to construct improvements to Ice Pond on Rocky Hill Road including installation of a new outlet structure and a new access road
- Project completion is anticipated in November 2024
- Questions about the project should be directed to the Office of Planning & Sustainability
Sewer Lining
- The City has contracted with National Water Main Cleaning Company for in situ lining of the sewer main on Cherry Street, Graves Avenue, Highland Avenue, Linden Street, Maplewood Terrace, Milton Street, Orchard Avenue, Ormond Drive, Union Street and Williams Street
- The project includes cleaning and inspecting sewer lines followed by pipe lining utilizing a technique called ultraviolet-light cured in place pipe (UV-CIPP)
- Brief disruptions to sewer service will occur during the process and notices will be handed out one (1) week in advance with a reminder notice 24 hours before any service impact
- See Notice to Residents (pdf) for more information
- Installation will run Monday through Friday, from 7:00 a.m. to 7:00 p.m. unless otherwise noted below
- This week, the Contractor will:
- Line laterals on Williams Street
- Line the main on Ormond Drive on Thursday (Oct 10th) evening, from 7:00 p.m. to 1:00 a.m.
Smith College Area Pedestrian Improvements
- The City has contracted with Pine Ridge Technologies, Inc. to install pedestrian improvements along Elm Street from Henshaw Avenue to Paradise Road and West Street from Green Street to Lower College Lane
- The project includes restriping crosswalk and pavement markings, replacing signage and installing rectangular rapid flashing beacons (RRFB) & flexible delineator posts
- RRFB posts will be installed in the coming weeks
South Main Street Sewer Repair
- The City has contracted with Geeleher Enterprises Inc. to make a sewer repair in the vicinity of 143 South Main Street
- Work is expected to begin in the coming weeks
Tree Protection Zones
- The fencing that has been erected in areas of the City around trees is to protect them during the different phases of utility upgrades and other construction excavations that are within fifty (50) feet of a public shade tree. This protection policy (pdf) is a requirement under the City’s trench permit policy (pdf) and ensures that public shade trees are kept free and clear from trunk and root damage.
- Excavation contractors have a phased approach to utility upgrades where they replace the main lines first over multiple streets then return at a later date to install new services to homes and businesses. Once they complete these phases they will remove the tree protection and may erect them at another location where work has yet to begin. Their schedule, while followed closely by the DPW permit system, is largely based on their operational capacity and contractor availability.
Washington Avenue Sewer Repair
- The City has contracted with Geeleher Enterprises Inc. to make a sewer repair in the vicinity of 101 Washington Avenue
- Work is expected to begin in the coming weeks
An overview of all current Public Works projects can be found by going to Current Projects.