Posted on: January 6, 2023

[ARCHIVED] Construction for the Week of January 9th

Highway Division Updates

  • Last week, the Highway Division:
    • Repaired potholes on Hillcrest Drive, Prospect Street and Westwood Terrace
    • Repaired curbs on Brierwood Drive, Francis Street, Gleason Road and Spruce Hill Avenue
    • Repaired, replaced and/or installed signs on Glenwood Avenue, Grant Avenue, Lincoln Avenue, Union Street and Walnut Street
    • Filled sand barrels throughout the City
    • Stockpiled salt deliveries
  • Yearly ward street sweeping is complete and will resume in Spring 2023
  • To report a pothole, please submit a request via the Pothole Repair Form; the largest potholes are filled first to alleviate hazards to vehicles; as hazards arise and are identified, they will be addressed

Ongoing Projects


Dryads Green Extension

  • The City has contracted with Geeleher Enterprises, Inc. to perform emergency work to stabilize the slope southwest of Dryads Green Extension in order to protect a nearby sewer system
  • The Contractor has removed deadwood, installed crushed stone & riprap and made limited drain pipe repairs; the work area has been seeded & mulched and additional sediment controls have been installed
  • The path from Dryads Green Extension to the Mill River is closed until further notice
  • The DPW will periodically inspect this area throughout the winter to confirm site stability

I-91 Bridges over Route 5, the Railroad and Hockanum Road

  • MassDOT has contracted with J.F. White, Inc. to construct roadway improvements to I-91 and at Exit 23 (formerly Exit 18)
  • The project will replace the I-91 bridges over Route 5, the Railroad and Hockanum Road and construct safety and signal improvements at the exit interchange
  • The project is scheduled to be completed in phases by 2025
  • I-91 southbound, no traffic impacts are anticipated this week
  • I-91 northbound, right lane closure at Exit 23 is scheduled this week, Monday through Thursday, from 9:00 a.m. to 2:00 p.m.
  • Route 5,
    • No overnight closures are scheduled this week
    • Placement of concrete mast arm signal foundations is scheduled this week for Tuesday and Wednesday, 7:00 a.m. to 3:00 p.m; police details will assist with traffic control
    • Shoulder closures will remain in place; no lane closures are anticipated during the day; motorists should be aware of trucks entering/exiting the work area
  • Hockanum Road, no traffic impacts or detours are anticipated this week
  • Questions about the project should be directed to MassDOT District 2, project #606552

South Main Street Sewer Rehabilitation & Lining

  • The City has contracted with Precision Trenchless LLC for in situ lining of the sewer main and service laterals on South Main Street from Beacon Street to Nonotuck Street
  • Brief interruptions to sewer service will occur during the process and notices will be handed out 24 hours in advance to inform residents of such interruptions
  • See the Notice to Residents (pdf) for more detailed project information
  • The Contractor will not be working this week
  • Work is anticipated to resume the week of January 23rd
  • One-way, alternating traffic will be in place as needed; police/flagger details will assist with traffic control; motorists should expect delays and seek alternate routes

Projects to Resume Spring 2023

Information & Notification

An overview of all current Public Works projects can be found by going to Current Projects.

Sign up for automatic notifications via the Notify Me system on the City's website. Please sign-in (at the top of the page) and then subscribe to the "Public Works" category under News Flash (at the bottom of the page).


Facebook Twitter Email

Other News in Public Works

Construction for the Week of September 18th

Posted on: September 15, 2023