Posted on: January 19, 2024

[ARCHIVED] Construction for the Week of January 22nd

Highway Division Updates

  • Last week, the Highway Division:
    • Repaired potholes on Bradford Street, Matthew Drive and Tara Circle
    • Removed, repaired and/or replaced signs on Bottums Road and Clement Street
    • Responded to snow event
    • Refilled sand barrels throughout the City
  • Lovefield Street remains closed
  • Annual ward street sweeping operations will resume in the spring
  • To report a pothole, please submit a request via the Pothole Repair Form; the largest potholes are filled first to alleviate hazards to vehicles; as hazards arise and are identified, they will be addressed
  • To report an issue with a traffic sign, please submit a request via the Traffic Sign Issue Form

Dryads Green Extension Drainage & Slope Improvements

  • The City has contracted with Geeleher Enterprises Inc. to construct drainage and slope improvements from the end of Dryads Green Extension to the Mill River; work also includes roadway drainage improvements
  • The project is substantially complete
  • Snow storage should be avoided at the dead end so as not to compromise slope integrity
  • Public Works will be on-site continuing post-construction observations throughout the winter

I-91 Bridges over Route 5, the Railroad and Hockanum Road

  • MassDOT has contracted with J.F. White, Inc. to construct roadway improvements to I-91 and at Exit 23 (formerly Exit 18)
  • The project will replace the I-91 bridges over Route 5, the Railroad and Hockanum Road and construct safety and signal improvements at the exit interchange
  • The project is scheduled to be completed in phases by 2025
  • I-91 southbound:
    • Daytime right lane closure Monday, Wednesday, Thursday and Friday this week, from 7:00 a.m. to 2:00 p.m., for site access
    • Daytime right lane closure Tuesday this week, from 5:00 a.m. to 3:00 p.m., to erect and bolt bridge steel
  • I-91 northbound:
    • No traffic impacts are anticipated this week
  • Route 5:
    • Daytime shoulder closures Monday through Friday this week, from 7:00 a.m. to 3:00 p.m., for concrete & slope work; motorist should be alert and use caution as trucks will be entering and exiting the work zone; a police detail will assist with traffic control
  • Hockanum Road:
    •  Daytime road closure Tuesday and Wednesday this week, from 7:00 a.m. to 3:00 p.m., to erect and bolt bridge steel; a detour (pdf) will be in place; a police detail will assist with traffic control
  • Questions about the project should be directed to MassDOT District 2, project #606552

Loudville Road

  • The City has contracted with Geeleher Enterprises Inc. to install a catch basin and drain pipe on Loudville Road in the vicinity of 81, 83 and 85 Loudville Road to address roadway drainage issues
  • Work is anticipated to be done in the coming weeks, depending on the weather

Winter Street Reconstruction

  • The City has contracted with Caracas Construction Corporation for the full depth reconstruction of Winter Street, including water & sewer mains and service connections and sidewalks
  • The project is substantially complete
  • Public Works and/or the Contractor will be on-site continuing post-construction inspections throughout the winter

Projects to Resume Spring 2024

An overview of all current Public Works projects can be found by going to Current Projects.

Sign up for automatic notifications via the Notify Me system on the City's website. Please sign-in (at the top of the page) and then subscribe to the "Public Works" category under News Flash (at the bottom of the page).