[ARCHIVED] Construction for the Week of November 30th


Highway Division Updates

  • Last week, the Highway Division:
    • Repaired potholes on Acrebrook Drive, Beattie Drive, Drury Lane, Holly Court, Turkey Hill Road and Westhampton Road
    • Patched a gate box at the Academy of Music
    • Loaded sand into the storage shed
    • Completed sewer markings on Damon Road
    • Maintained ditches on Park Hill Road
    • Continued preparations for winter operations
  • Street sweeping continues in Ward 2
  • To report a pothole, please submit a request via the Pothole Repair Form; the largest potholes are filled first to alleviate hazards to vehicles; as hazards arise and are identified, they will be addressed.

Rocky Hill Road (Route 66) Drainage Improvements

  • The City has contracted with Geeleher Enterprises, Inc. to make roadway drainage improvements on Rocky Hill Road in the vicinity of the Hampshire County Jail & House of Corrections
  • Drainage improvements are complete
  • Paving the trench cut and driveway entrance should be completed by mid-December

North Farms Road & North Maple Street Paving Project

  • The City has contracted with Palmer Paving Corp for pavement reclamation on North Farms Road, from the Williamsburg Town line to the intersection with North Maple & Mountain Streets, and North Maple Street, from Mountain Street to Bridge Road
  • The project will also include the following features:
    • Roadway drainage improvements on North Farms Road in the vicinity of Country Way
    • Repaving the walking path into the Fitzgerald Lake Conservation Area
    • Extending the North Maple Street sidewalk to provide continuous sidewalk from Bridge Road to the basketball parking lot at Arcanum Field
    • Radar speed signs at strategic locations on North Farms Road
    • A new crosswalk on Bridge Road connecting the Mountain Street sidewalk to the sidewalk along the south side of Bridge Road; this includes the installation of two rectangular rapid flashing beacons that will alert vehicles traveling on Bridge Road that pedestrians are crossing
  • Crews will continue working on driveways top course, shoulder treatments, resetting mailboxes and installing traffic signs this week
  • Line striping may occur this week depending on temperatures
  • Officers will be on-site to direct traffic, but expect longer than usual delays on North Farms Road and seek alternate routes if possible

Forbes Library Drainage Improvements

  • The City has contracted with Jack Goncalves & Sons Inc. to make drainage improvements at Forbes Library
  • Work includes removal of trees and installing drainage improvements down the slope south of the library's parking lot and along the rail trail heading east from the library
  • Work continues this week on slope stabilization measures above the rail trail and drainage improvements along the rail trail; the rear half of the parking lot will be used for construction activities
  • Equipment may be working along the rail trail from the New South Street Bridge to 500 feet west of the bridge and officers may be present during work hours; please seek alternate routes

Bridge Street, Damon Road, Interstate 91 - Exit 19

  • MassDOT has contracted with Baltazar Contractors, Inc. to construct a roundabout and associated improvements to the Interstate 91 - Exit 19 interchange at the base of the Coolidge Bridge
  • The project is scheduled to be completed by June 2021
  • Temporary line striping defining the completed roundabout layout is in place
  • Slight lane shifts will be required for sidewalk, island work and sign placement
  • Final paving and line striping of the roundabout will occur in Spring 2021
  • Questions about the project should be directed to MassDOT District 2

Damon Road Reconstruction

  • MassDOT has contracted with Gagliarducci Construction, Inc. to reconstruct Damon Road from the bike path to just beyond the intersection with King Street, North King Street and Bridge Road
  • The project will provide intersection and traffic signal improvements, extended sidewalks, a shared use path and other safety improvements
  • The project is scheduled to be completed by June 2023
  • Utility relocation, drainage improvements and water & sewer replacement will occur prior to full depth roadway reconstruction
  • Environmental controls, building demolition, utility relocation and drainage work this fall will all take place off-road
  • Questions about the project should be directed to MassDOT District 2


An overview of all current Public Works projects can be found by going to Current Projects.